Alexanderson Earthmover is a medium size contractor supplying services to the following project types: Civil Infrastructure,Reclamation, Quarrying,Subdivision,Mining,Dam Construction,Earth Works Formation,Plant Hire Home Capability Experience People Fleet Systems Gallery Contact Us

Experience

South East QLD Correctional Precinct - Baulderstone Queensland

Civil works for stage one of the new prison located at Gatton, 500 Men & 300 Women

  • 900,000m2 Clearing
  • 850,000m2 topsoil removal
  • 1.2 Million Cut to Fill – Level 1 Supervision
  • Utilising Majority of the AE Fleet in excess of 60 Machines
  • Working with Cultural Heritage & Wildlife monitors
  • 2ML of water consumption per day includes pumping water 5km
  • 5 kilometres of drainage systems
  • HDPE Lined water retention basins
  • 6 kilometres of main roads built to QLD Main Roads Specifications
  • Construction of HDPE Lined waste water and evaporation ponds.
  • Bulk earthworks 7 months – completed project 9 months

SEQCP - Water Retention Basin

SEQCP - Continuous Basin Pour

Ash Storage Area Extension Project - Stanwell Corporation Limited

Stanwell Corporation Limited awarded Alexanderson Earthmover the Ash Storage Extension Project at the Stanwell Power Station based on our extensive dam construction experience and value for money contracting attitude.

The scope comprised the clearing of the site, construction of extensions to the ash containment embankments (Approx 350,000m3), evaporation ponds, drainage, topsoil and revegetation works. AE mobilised a PC750 Komatsu excavator with 50T Komatsu dump trucks to excavate load and haul to the Dam walls, diversion bunds and spillways.

With material selection and management being the key requirement of the project to meet the strict quality assurance criteria, AE developed specific work methods and procedures utilising 50T Komatsu water cart, 825 Compactors and Cat 14G graders fitted with GPS to ensure quality compliance thereby achieving a successful outcome for the client.

 

Cooroy to Curra - Abigroup Contractors

Alexanderson Earthmover were engaged by the successful tenderer (abigroup) on the Cooroy to Curra Main Roads contract to supplement their own construction fleet with additional Major plant and skilled operators for construction.

The project scope consisted of the removal of 7 Million cubic metres of material to tight time constraints. Plant utilised were PC 1100 Komatsu excavators with a fleet of 50T Rear Dump Trucks. Final trim batter work was undertaken with several PC 300-8 excavators (with GPS) providing fast efficient and pegless operations. AE graders were utilised in the bulk earthworks crews for haul road maintenance and management of fills and was accomplished by our skilled final trim operators with GPS capability.

The large volumes of material hauled through the project required our fleet to interact with other construction traffic extensively and was achieved without incident and to the satisfaction of our client.

Yarrabee Coal Mine - Yarrabee Coal Company

AE was awarded an earthworks contract at Yarabee Coal Mine comprising the stripping of 150,000m3 topsoil, construction of haul road and associated drainage works utilising a fleet of 4 x 631G Cat Scrapers, D9T Dozer and Cat 14H Grader.The contract was secured in recognition of our past performance on projects undertaken with management within Yarabee Coal Company. Our excellent safety record combined with our late model equipment made it an easy choice for our client.

Reclaimed Area A6 Rehabilitation – Oakey Creek Coal Mine - Xstrata Coal

Topsoiling and Ripping of The A6 Reclaim Area was awarded to AE mid October 2009. Approximately 81 Hectares of ripping and over 52,000 cubic metres of topsoil was placed on batter slopes exceeding 1:3 utilising 375 Komatsu Dozer and 631E Scrapers to the clients specification.

The innovative rehabilitation methodology developed by the company during the past 15 years was utilized on the project to the satisfaction of the mines environmental division. Working together with the engineering staff the AE team achieved the desired results, on time and under budget.

 

Wonarah Mine Project - Minemakers Limited

Wonarah Mine is 3 hours by car from Tennant Creek and 4 hours to Mt Isa. The remote area project consisted of the provision of suitable plant and supervision to excavate a trial mining pit to bulk sample 170,000 bank cubic metres of rock phosphate.

Earthworks consisted of the removal of overlying material and rock phosphate. This material was stripped utilising an excavator and truck operation. PC850 Komatsu Excavator and 6 No. 465-5 Komatsu 50T Rear Dump Trucks removed the underlying rock phosphate into stockpile ready for transportation to potential customers in India, Pakistan and North America.

Due to the remote nature of the Project, Alexanderson Earthmover established on-site maintenance facilities to service the plant thereby ensuring high levels of plant availability.

Current Productivity is exceeding the client’s objectives and they are on track to be in full production by mid 2010 to take advantage of the anticipated increase in demand for rock phosphate on the world market.

Waterford - Tamborine Road Main Roads Project

With the upgrade of Waterford - Tamborine Road requiring cut to fill of 130,000m3 a fleet of  631E Cat scrapers and 825G Cat compactors were mobilised. To enable the cut to fill operations to begin soft ground treatments of different methods were applied to enable bulk earthworks to begin, in areas moisture affected material was removed and other areas Bidum fabric and rock layers were chosen to found the road pavement.

In some areas final trim was undertaken by 16H Cat grader using GPS control with a no peg policy saving time with no survey required. With batters requiring final trim in areas steeper than grader grades a PC 300-8 Komatsu excavator has been mobilised with a highly skilled final trim operator to enable detailed trim one pass completed works.

With Hard rock encountered in cuttings, the decision to mobilise a 475 Komatsu dozer was made to reduce the need to drill and blast. This also enabled the hard rock material to be ripped using a methodology to manufacture the hard rock sand stone so the end product could be used in embankments.

  • 130,000m3 cut to fill
  • 4,000m3 top soil
  • 6,000m3 unsuitable

Northern Access Road Project - Leighton Contractors QLD 4 /2009

Excavate, load, haul and place 150,000m3 material to Main Roads QLD standard specification

PC750 Komatsu excavator, Komatsu 465 rear dump trucks & 140H cat grader.

Material hauled to Brisbane Air Port Corporation Car Park Project.

Thiess Services Swan Bank  3/2009 -

Supply Major plant for earthworks including PC 650 Komatsu excavator, 825G Cat compactor, Komatsu heavy haul 50 tonnne water cart.

Provision of skilled plant operators for Thiess owned machinery

Swanbank Landfill Waste Disposal Facility – Ipswich

Alexanderson Earthmover was engaged by Swanbank Waste Management to remove spontaneous combustion material from an existing dump site after recent heavy rains had caused a slip onto Swanbank Road. These works were performed pursuant to the Coal Mining Act under the constant scrutiny of the Department of Mines and Energy and the Environmental Protection

Agency. Alexanderson’s were appointed SSE for the project site.

Plant selected to undertake the works consisted of PC650 Komatsu Excavator, D9T Caterpillar Track Dozer and Scania Watercart with 13,000lt capacity with high pressure fire fighting capabilities.

As limited data existed on how spontaneous combustion material reacted in its own environment with different elements and

exposure ratios, the Department of Mines and Energy subsequently used this work as a test case.

Specialised heat guns and gas monitoring equipment were utilised to measure the temperature and discharge of gases of the material in its natural state and throughout excavation Material temperatures varied between 50 degrees and up to 380 degrees

Risk assessments and JSEA’s were completed and updated daily due to the nature of the material and handling requirements.

Continual monitoring and data collection was compiled throughout the excavation allowing Alexanderson Earthmover and the client to make informed decisions regarding the safety of their personnel and plant to deliver a safe and effective outcome for all parties.

South West Transit Corridor Package D Bulk Earthworks Contract

Bulk Earth works comprising of 400,000 cubic metres with 55 metre vertical cutting with berms, material management essential to the success of the project with pavements material for upper zone sourced from steeply dipping layers in the cut surrounded by poor quality materials used in common fill embankments having to be separated.

  • With haulage up to 4 kilometres

  • Komatsu 465 50 ton dump trucks were selected to haul material long distance, utilizing a PC1100 and PC750 Komatsu excavator loading up to 8 trucks at any time testing and programming was essential.
  • Water for construction being identified as a major concern at tender Alexanderson Earthmover came up with a solution to the dry site by
  • laying a high pressure poly pipe line 9 Kilometres to a holding dam on site and pumped water 24 hours a day as required giving the site ample water for construction.
  • With large volumes of material to handle compaction and conditioning of fills to allow continuous placement AE utilized 825G / 825C / 835B Cat compactors with a no failure result in bulk earthworks and upper zone placement of materials.
  • Haulage of water from a centralized holding dam was carried out by 2 x 465 Komatsu 50 ton water carts and supplemented by a 651B Scraper water tanker when required in warmer conditions.
  • GPS equipment utilized on site comprising of a PC 300-8 Komatsu excavator fitted with Top Con GPS maintained all cut and fill batters, a 16H and 14G / 16G Cat Graders fitted with GPS and Millimetre control systems were used for all fill placement and final trim works.
  • Encountering solid sandstone in the cut AE utilized 475-3 Komatsu dozers to rip, separate a stock pile material for use in common fills and upper zone embankment giving best rip penetration and stock pile capacity

South West Transit Corridor Project - Plant Hire

Bulk Earthworks comprising 2.5 million cubic metres cut to fill and spoil. Provide work shop facilities to maintain large plant fleet:

  • 1 x D11R CAT dozer
  • 2 x D10R cat dozers
  • 2 x D375 komatsu Dozers
  • 14 x 631E Cat scrapers
  • 2 x 835 Cat compactors
  • 4 x 825 Cat compactors
  • 2 x 475 Komatsu rip dozer
  • 1 x PC1100 Komatsu excavator
  • 1 x PC800 Komatsu excavator
  • 2 x PC710 Komatsu excavator
  • 2 x 50 ton water trucks
  • 2 x PC300 komatsu excavators
  • Fleet of 50 ton 465 Komatsu dump trucks
  • 2 x 16H GPS Graders
  • 2 x 14G/H Graders
  • 2 x 140G Graders

Lake Lindsay Mine Project - Haul Road Construction
Contract for the construction of a 35 metre wide Haul Road, 8.9km long, to be used by Anglo Coal's new 793 Cat dump trucks.
  • Bulk Earthworks comprising 300,000m3 of cut to fill
  • Drainage CSP Ranging from 400mm diameter to 1650mm diameter
  • Win select CBR 20 materials for pavement sub-base course from borrow
  • Haulage of 60,000 m3 of CBR 45 pavement base course and placement to finished level. All trim carried out using GPS Grader systems.

Burdekin to Moranbah Water Pipeline Project - 600 mega litre Dam
  • Top soil stripping of Dam foot print and Borrow areas with 631E scraper fleets 60,000m3
  • Dam Foot print foundation stripped of unsuitable material to stockpiles 150,000 m3
  • Treatment of foundation ready for placement of conditioned clay materials
  • Treatment of clay borrow material for Dam wall construction 300,000m3 including excavation load haul and placement on a rotating 24/7 roster
  • Conditioning of materials carried out using irrigation methods 24 hours per day
  • Treatment of zoned material for Dam wall construction 200,000 m3 including excavate, load & haul with fifty ton Komatsu HD465 rear dump trucks and placement on a 24/7 rotating roster.

Radius Industrial Park Larapinta for the Potter Group
  • 1 million m3 cut to fill with Level 1 Supervision
  • Removal of 500,000m3 of unsuitable from old sand mining areas adjacent to Oxley creek
  • Management on-site of 200 ML of highly contaminated water, treatment and release into environmental sensitive Oxley Creek.

Delfin Lakes Entrance Project - Bulk earthworks

  • 100,000m3 in sandstone
  • Cut to fill with 1km lead

Springfield Future Dam Project - Plant Hire

  • Supply Komatsu D475-3 Dozer for bulk pushing 50,000m3 for Dam Embankment & 2 x Cat 835 Compactors

Hay Point Coal Infrastructure - Bulk earthworks

  • Excavate, load & spread 500,000m3 of overburden

Pacific Highway Brunswick Heads - Plant Hire

  • Supply Komatsu D375 Dozer for Rip & Stack. 2 x 30 Tonne Excavators for detailed batter trimming

Titian new Gold Coast NRL Stadium - Reclamation wick drains and preload, Site preparation

  • 45,000m3 pre load removal, wick draining of preload area
  • Placement of permeable sand layer, 45,000m3
  • Level 1 place, condition & compact, 190,000m3 of preload replacement

Wivenhoe Dam - Bulk earthworks, Drainage, Dam construction

  • Bulk Earthworks 500,000m3 sandstone
  • Detailed drainage across dam wall
  • Building spillway core

Highway Commercial Springfield Future Commercial Shopping Centre & Hotel - Bulk earthworks, Site levelling

  • Bulk Earthworks 100,000m3 of moderately weathered sandstone
  • Reprofile 10mtr high batters & construct bolder walls including shotcreting

Boral Construction Materials Ormeau Quarry - Haul road construction, Quarry development

  • Construction of new haul road
  • Excavate, load, haul & spread 200,000 Tonnes of overburden

Kogan Creek Power Station - Plant Hire

  • Supply of equipment & personnel to assist 1.8 million m3 bulk earthworks
  • Supply of heavy ripping equipment D475 & D375 dozers, large water truck & small excavator for detailed work

Merrimac Waste Water Treatment Plant - Bulk earthworks, Contaminated waste removal

  • Clearing, demolition of structures including removal of asbestos
  • 100,000m3 bulk excavation for retractors including working around existing treatment plant and detailed excavation

Millennium Open Cut Coal Mine - Rail formation, Road formation, Bulk earthworks

  • Rail loop
  • Access road
  • General bulk earthworks

Austral Bricks

  • Contracted to source, win, load and place in layers clay & shale for brick manufacture

Gold Coast City Council Reservoir Site - Water infrastructure

  • 190,000m3 Drill and Blast in quartzite, construction of platform for reservoirs 40m vertical cut into the side of an environmentally sensitive hill side.

Clover Hill Estate

  • 200 Lot Subdivision - Residential subdivision
  • 310,000m3 Level one supervision

Bendigo Relocatable Buildings - Bulk earthworks, Site levelling, Drainage

  • 10 Acre Industrial Premises
  • Bulk Earthworks & level 1 supervision
  • Trimming of site
  • Drainage

Robina Land Corp Robina Site Development - Bulk earthworks, Preload

  • 100,000m3 Level one supervision
  • 180,000m3 Preload Relocation

Hope Island - Preload

  • Excavate load and haul sand preload to be reused at batching plant 120,000m3

Port of Brisbane - Preload

  • Removal and relocation of preload stock piles 600,000m3

Springfield/Greenbank Connection Road - Road formation

  • 9km - Cut to fill 210,000m3 in sandstone, 47,000m3 topsoil strip, level one compaction & trimming of sub grade.

Main Roads, New England Highway

  • 5km of new aliment 250,000m3,bulk earthworks, drill & blast & trimming contract

M1, Pacific Motorway - Early Works package

  • Construction of new service roads including drainage structures, supply & place 210,000 tones of road embankment material.